Home / Projects / Modernisation
Irrigation Pumping Station Automation Panel Refurbishment — Yamula Mansap
A modernisation project in which automation panels at the end of their service life were rebuilt to current standards. This is the situation irrigation unions meet most often: the pumps and hydraulic equipment still work, and what has aged is the electrical and automation side. Here the mechanical equipment was retained and only the control and automation side was renewed.
Scope of work
- On-site survey of the existing system and preparation of the refurbishment design
- Manufacturing of automation panels to IEC 61439
- Field control panel with operator terminal
- Renewal of the motor drive panels
- Rewriting of the PLC software
- Removal of the old panels, installation of the new panels and commissioning
Technical solution
Setting the boundary of the refurbishment
The first step in refurbishment work is establishing clearly what will be replaced and what will stay. The site survey showed that the existing motors and hydraulic equipment could remain in service, so the scope was limited to the control and automation side, which reduced the investment cost.
Panels to IEC 61439
The new panels were manufactured to IEC 61439, the standard for low-voltage switchgear and controlgear assemblies. This is not merely a certification matter: internal separation, temperature-rise behaviour, short-circuit withstand and continuity of protection are all designed to the requirements of that standard.
Field control with operator terminal
So that station personnel can work without depending on the control centre, a touch operator terminal was fitted to the field control panel. Pump states, levels and alarms are visible at the station as well.
Managing the outage
Removal of the old panels and installation of the new ones were scheduled outside the irrigation season, so the water delivery calendar of the stations was not affected.
Outcome
Both stations were returned to service with panels built to the current standard and with rewritten software. Dependence on obsolete hardware with no available spare parts was removed, and the operations team can now see the system from the station itself.
From the field and the SCADA screens



Our services used on this project
Engineering and System Design
Requirement analysis, system architecture and detailed engineering
Details SV-02PLC / DCS / RTU Software
Custom control software across multiple vendor platforms
Details SV-04Electrical and Automation Panel Manufacturing
Project-specific MCC, distribution, control and PFC panels
Details SV-05Field Installation, Commissioning and Maintenance
Installation, commissioning, training and 24/7 technical support
DetailsOther reference projects
Konya Ereğli İvriz Left Bank Irrigation SCADA System
View the project Pumping StationASKİ — Automation Panels for 12 Pumping Stations
View the project MV SCADAKars Airport MV/LV SCADA Project
View the project Process AutomationBarajyol İnşaat — Cement Plant Automation Project
View the projectDo you have a similar project?
Send us your specification or bill of quantities; we will review the scope and return a priced quotation.